Hi,
Should Multiple Zone systems in the MNECB Reference building have Supply Air
Temperature reset?
I?ve always used it because I know EE4 has the cooling coil reset for
reference buildings in DOE2.1E (COOL-CONTROL = WARMEST).
The reason I ask is because Table 5.4.1.B of the MNECB Performance
Compliance for Buildings says ?Supply air temperature from secondary system
to terminal units is constant at 13?C (55?F).? for Multiple Zone Systems.
The sentence still exists in the 2011 NECB.
Thanks,
Aaron Smith, P.Eng