No cooling load in high EPD zone_data center

2 posts / 0 new
Last post

Hello,

I'm trying to model a data center with 200kW internal load. It has
dedicated PAC to meet the cooling load demand but after successfully
running the simulation, i don't get any cooling load in the summary report.
I tried to check the accuracy with equest default 5 zone model and i get
load of around 175 TR which makes sense. I tried everything in my working
model but unable to resolve this problem. Does anybody has come across
similar problem? Any help would be appreciated.

Thanks in advance.

--

Javed Iqbal, LEED AP, CEA

javed's picture
Offline
Joined: 2011-04-11
Reputation: 0

Javel;
?
It would help to see your .INP and .PD2 files to access. If you have package cooling. the SS-D report should show cooling load, but no cooling will be shown in the Plant reports.
?
If you can send your inputs, we might have a better shot at helping you.
?
John R. Aulbach

John Aulbach's picture
Offline
Joined: 2011-09-30
Reputation: 1