I am simulating a core and shell office building with system 6 for my baseline.
The?design case is?a two pipe fan coil units at common areas and all tenants
will have chilled water pipe provision for them to?tap their fan coil units.
Based in CS Appendix 6?under step 1, model the HVAC system as described in the
design documents. My question is:
1. Does that mean I will be modeling only the common since it only the areas
that were designed?
2. Do I need to also include the tenant areas?
3. Since the tenant areas have FCU pipe provision, do I model it as FCU or do I
have to model it as system 6 which is my baseline case?
Thank you all in advance.
Jaigath