Which 2 of the following are legitimate options for calculating cost savings for LEED EA credit 1?
Any exact local rate structure
EIA statewide average rates
The exact rate structure to be used for the actual building
National averages published by EIA
There are a number of rules regarding unmet load hours APPENDIX G: the combined heating and cooling hours are listed below for the baseline building. Select the corresponding MAXIMUM number of unmet load hours for the proposed building
You lose points by selecting incorrect options. You may leave an option blank to avoid losing points.
How many times must the baseline building be calculated for the performance rating method?
Once only.
Twice. Calculate the actual orientation and an additional rotation of 180 degrees.
Four times. Calculate the actual orientation and 90, 180, and 270 degree variations.