Good Morning,
I got the following Warning in my detailed output file.
BLOCK-CHARGE Cust 1 Elec TOU IS USED IN A TIME-OF-USE
FORMAT, BUT IS NOT TOU-SEASON-LINKED TO ANY OTHER
BLOCK-CHARGES FOR SEASONAL CHANGES. THEREFORE, ANY
SEASONAL CHANGE MUST OCCUR ON THE BILLING DAY OR
ERRORS WILL RESULT. REFER TO REPORT ES-F.
I think this is ok, but I wasn't sure exactly what it meant so I went back
into the design wizard to take a look at the utility rates. I have two
seasons setup in my utility screen. I changed the uniform charge for kW and
kWh for both seasons to see what effect this would have. When I clicked
finish, to return to the detailed mode I now get an error which says "An
invalid argument was encountered" and then I have to reopen the project. I
have tried restarting equest and resetting the values changed, but
essentially it seems like I cannot use the wizard anymore. Has anyone ever
had this problem, or have any clue how to fix it?
Thanks,
Michael
____________________________
Michael Shields, EIT