Hey all,
I've created my proposed model, did a "save as" and created my baseline model, and changed all of the HVAC systems etc. to the required 90.1 standards. I ran the simulations and exported the LEED report and noticed my receptacle loads aren't the same-the baseline is 12% higher than the proposed. I've compared schedules, equipment loads, and square footages, and they are identical in both the proposed and baseline models. Is there something else I should be looking at?
Thanks for your help!
Stephanie Andersen