baseline % window area in trace

3 posts / 0 new
Last post

Just wanted to check and see if there is an easier way in Trace to modify the base building to account for percent glazing in the baseline building.

My proposed building has 28% windows (from the buidling areas report in trace).  This is less than 40% so I need to use the 28% number.

In order to change this in trace, do I have to get in to each room and change the windows from quantity to 28%?

That seems like a lot of data entry - Is there an easier way?

Thanks