To All,

How do I set up my "efficient" project run once I have created my ASHRAE
compliant baseline building model? I am currently working in detail mode.
Can this only be done from the wizard? I guess the better question is how do
I set up "RUN 2" in the model I've just built with different wall, HVAC etc.
inputs.

My current experience with project runs is GBS does eQuest work the same
since the DOE-2 engine powers them both?

Thanks,

PETER HILLERMANN

Peter Hillermann's picture
Joined: 2011-09-30
Reputation: 0

Peter,
In the detailed interface you will need to set these up as parametric runs (Tools/parametric runs).

Vikram Sami, LEED AP

Sami, Vikram's picture
Offline
Joined: 2011-09-30
Reputation: -1

Sami,

Thanks, Seems like I am going to be filling out a lot of information today.
It seems that this is exactly the same as GBS only in eQuest you can create
your own wall constructions and HVAC info etc. I hope that GBS will allow
this in their alternate designs in the future or maybe I haven't found out
how to manipulate their interface yet. You know there's always that one
radial button you forget to check that makes everything work.

Thanks,

PETER HILLERMANN