LEED system 5

7 posts / 0 new
Last post

Salutations!

I just completed a LEED model, but after reviewing the data results, I think something is wrong.

The baseline building is showing no energy used for space heating, heat rejection, and service water heating. I have the 2 boilers modeled, per G3.1.3.2. This sort of makes sense because the model was showing high unmet heating hours, while the proposed building had had unmet cooling hours (successfully resolved).

I set up the system 5 equipment (Packaged VAV with reheat) in the wizard, but it doesn't seem to show a heating component in the DDE. I'm going to keep looking, but wanted to see if someone could point me in the right direction.

Regards,
Matt Clough

Matt Clough's picture
Offline
Joined: 2012-03-01
Reputation: 0