Hello, everyone.

I have met a problem during my simulation with useing EQUEST 3.61.

**WARNING**********************************************************************
ZONE E1 ENE Perim ML Zn (ML.ENE2)
might have insufficient heating capability.
Check that the SYSTEM or ZONE HEATING-CAPACITY plus this
ZONEs BASEBOARD-RATING is adequate to maintain the ZONE
specified DESIGN-HEAT-T for the calculated peak ZONE load
(see LS-A or LS-B for the ZONE peak load.)

SYSTEM E1 Sys1 (MZS) (ML.ENE2)
which supplies the above listed ZONE, has a design heating
coil exit temperature, HEAT-SET-T,(plus any zone reheat)
below its MAX-SUPPLY-T or the ZONE DESIGN-HEAT-T, which
might account for the insufficient heating capability.

I hace checked the

AIR SIDE
SYSTEM E1 Sys1 (MZS) (ML.ENE2)
HEATING
ZONE ENTERING MAX SUPPLY TEMP

This temperature is higher than the above zone's heating HEATING DESIGN TEMPERATURE.

How can i changing my setting to avoid this warning.

May be this warning is the reason of the UNMET HEATING LOAD.