Dear All,

My efforts in modelling a building with 2 pipe fan coil system has
resulted in the following: I am using heating / cooling schedules in my
2-pipe loops (Loop Operation: Schedules) and I have a snap location that
is set to outdoors. I also have a dead band of 15 deg. (between 50 and 65
deg.) in my schedules between heating and cooling.

How does one further make sure that the system operates in either heating
or cooling for a minimum number of hours before changing over?