I was curious if anyone knew whether the following is allowed in
accordance with Appendix G (and/or LEED):
If have a hotel where the baseline system is PTAC, and those units are
intended to be the source of ventilation air, I have to have the fans
run continuously per Appendix G.
If my proposed building has a central OA delivery system that introduces
OA directly to each room, can I have that system run continuously and
allow my FCUs in each hotel room to run intermittently?
Thanks for any advice!
James Hansen, P.E., LEED AP