Dear Sir,

Your answer to my previous questions was very helpful. Since we have other
projects which are using LEED-NC-Multiple buildings. My doubt is as follows
"Project site is away from the water body by 98.08 ft but protruding towards
water body by 15 ft from next floor level "due to this it may affect on the
site selection (SS Credit.1). Also note that site area is reclaimed. Please
do the needful