how to turn off heat/scheduling

4 posts / 0 new
Last post

I am getting a heat load in the middle of the cooling season.? I don't believe it.? the system is VAV, chilled water with reheat coils at the boxes only.? Office Building?in a semi-tropical zone (3).?

I understand that I should be able to turn the heat off/make unavailable, but the instructions on how seem cryptic.....that or my brain is overloaded.? Can someone provide a quick answer ton how to do it?

Thanks!

Paul Brooks's picture
Offline
Joined: 2011-09-30
Reputation: 0

Hi Paul,

Click through all the tabs in the Heating inputs and make sure you don't have any supplementary heat in there that shouldn't be included. I believe eQuest add a supplementary furnace automatically to all systems and you have to remove it. I hope this helps.

Kristy Walson, PE, LEED AP

Walson, Kristy's picture
Offline
Joined: 2011-09-30
Reputation: 0

for my base LEED model I am using electric re-heat at VAV boxes.? I have the issue there.? I think I just have to turn it off to make all of this work.....i think.

Paul Brooks's picture
Offline
Joined: 2011-09-30
Reputation: 0

Setting Maximum Heating Rate to 1 Btu/h gets rid of heating. On air-side
hvac zone parameter screen, under heating tab. Change 1 time using your
screen then find it under the spreadsheet option where you can copy and
paste.

Note: you may still see a heating load on SV-A but you should have no
heating energy use.

Another issue comes to mind: how to do this using a schedule so you can have
heat when you want it.

Peace,
Carol