Now that we're solidly into 2017, the predominant historical year weather file of interest
is 2016. However, over the past month I've had at least 5 complaints there's something
wrong with my 2016 weather files because it crashes their software, Helios and Climate
Consultant being two such programs that I remember, and maybe Trane.

In all four cases, the reason for the crashes lies not in the weather data, but the
failure of those programs to accept a Leap Year with 366 days! I've communicated this
glitch to the developers of Helios and CC, but until the programs are modified, the only
thing to do is to manually delete Feb. 29 from the files in order for it to work.

I'm surprised that so many people think of Leap Years as an irrelevant anomaly. It's not a
rare astronomical phenomenon like the conjunction of three planets that occurs once in a
century; it happens a quarter of the years! I mean, if I tell you I have an algorithm
that works 75% of the time, would you want to use it? :-)

Okay, so it's just an extra day in February that can be deleted for convenience. But
isn't the purpose of using a historical weather file to compare to actual data, e.g.,
utility bills, so do we also prorate the energy consumption, HDD, etc., for February? And
once Feb. 29th is deleted, won't the Day of Week be out of sequence for the rest of the
year, e.g., with the actual weekends now falling on "Fridays" and "Saturdays" in the
simulation? All these issues because somebody decided not to include the extra Leap Day.

With the CSV, EPW, and other text files, you are free to hand edit out Feb. 29th if you
choose, but what about the DOE-2 *.BIN (*.BINM) binary files? It might surprise a lot of
even experienced DOE-2 users, but the *.BIN/*.BINM files always include Feb. 29th. In
fact, the DOE-2 weather file format has room for 384 days, since the binary data are
stored in two arrays of 1560 (4 numbers for each hour, or 16 days), with room for 32 days
for each month! When people complain that DOE-2 doesn't handle Leap Days, the fault lies
in the DOE-2 code, not the weather data; DOE-2 simply always reads 28 days for February
and then jumps automatically to March. In fact, the code actually has a variable for
ILEAP (1= yes, 0=no), that is being used only to get the right DOW.

For years, I've toyed around with the idea of testing the use of ILEAP and see how easy is
it to get DOE-2 to read and simulate February 29th. I've braced myself this time because
the last time I mentioned this problem someone recommended, "use EXXXXXXXXX" !

Somewhat tangential to this is a warning to those many DOE-2 users who have asked for
"composite weather files" that span two years, e.g., Jan 1- June 30, 2017, followed by
July 1 - Dec 31 2016. Since DOE-2 accepts just one value for the keyword YEAR, make sure
that the Day of Week doesn't get fouled up after the change-over day. You may need to
redefine all the Days of Week to avoid the problem mentioned two paragraphs back. (Just a
friendly suggestion...)

Joe

--
Joe Huang
White Box Technologies, Inc.
346 Rheem Blvd., Suite 205A
Moraga CA 94556
yjhuang at whiteboxtechnologies.com
http://weather.whiteboxtechnologies.com for simulation-ready weather data
(o) (925)388-0265
(c) (510)928-2683
"building energy simulations at your fingertips"

Bldg simulation's picture
Offline
Joined: 2016-04-13
Reputation: 400

Joe,

Thank you for bringing up the leap year issue! I have also been surprised how people don't seem to have a way to deal with it. Although I deal with new construction 99% of the time instead of existing buildings, I have thought about the topic and have talked to people at conferences about how they deal with modeling leap years. I never got a good answer.

I figured that the program would have to somehow skip over February 29th. Like you mentioned, the program might ignore it in the weather file or you might have to manually delete the day from the weather file. But then the days of the week don't match for the rest of the year! The weekend weather happens in the model on days with Friday and Saturday occupancy schedules. (Or maybe it's Sunday and Monday...I don't feel like figuring that out right now.) If the model starts with January 1st on the correct day of the week, January and February would be right, but the rest of the year would be offset a day. It seems that it would be a bit better to have January 1st in the model be the day of the week before it really occurred so that 10 months would be right and 2 months wrong instead of 2 months right and 10 months wrong.

I would be interested in hearing how those of you who do calibrated models deal with leap year. Do some programs have a way to include leap day?

Keith Swartz, PE | Senior Energy Engineer
Seventhwave
608.210.7123 seventhwave.org

Bldg simulation's picture
Offline
Joined: 2016-04-13
Reputation: 400

Hi Keith,

To answer your specific question about how other tools deal with leap years, IES VE has the ability to handle leap years with a simple check box in the simulation calendar. It's been an option in the VE for some time now.

As Joe notes, it's a small but significant thing particularly when dealing with existing building calibration.

I can't embed images in this email reply or I'd include an image of the functionality. :-)

Nathan Kegel
Vice President IES Midwest
O:
763.276.9981
M:
415.420.9314
http://www.iesve.com

Integrated Environmental Solutions Limited. Registered in Scotland No. SC151456
Registered Office - Helix Building, West Of Scotland Science Park, Glasgow G20 0SP
Email Disclaimer

Latest News: IES VE was ranked as the #1 energy modeling tool for design engineers by the AIA 2030 Progress Report.

Bldg simulation's picture
Offline
Joined: 2016-04-13
Reputation: 400

Joe...

Climate Consultant ignores the 29th day of February after giving the
user the message -
"The EPW File has an extra day (February 29th). Climate Consultant
ignores this day for calculations."

If anyone is having a problem with the current release of Climate
Consultant crashing over February 29th, please send us a copy of the
data file to test

Murray Milne
Research Professor
UCLA, Department of Architecture and Urban Design, Los Angeles, 90095
All our ENERGY DESIGN TOOLS software can be downloaded free from:
www.energy-design-tools.aud.ucla.edu

Bldg simulation's picture
Offline
Joined: 2016-04-13
Reputation: 400

Murray,

Thanks for the clarification. In your honor, I will send you the file for
CA_LOS-ANGELES-DOWNTOWN-USC_722874_16.zip via separate e-mail so that it doesn't clog up
the airwaves. Does CC just give that warning, or have you modified the program to include
the 29th day ?

Joe

Joe Huang
White Box Technologies, Inc.
346 Rheem Blvd., Suite 205A
Moraga CA 94556
yjhuang at whiteboxtechnologies.com
http://weather.whiteboxtechnologies.com for simulation-ready weather data
(o) (925)388-0265
(c) (510)928-2683
"building energy simulations at your fingertips"

Bldg simulation's picture
Offline
Joined: 2016-04-13
Reputation: 400

David,

It's occurred to me that what you're suggesting in removing December 31st does not work
for the following reasons:

1. DOE-2 "automatically" skips Feb. 29th because DOE-2 weather is stored in monthly "chunks".

2. Continuing the run beyond Feb. 28 means that the weather data are right, but the Days
of Week are offset by 1.

Therefore, the "best" way to get this right (and it's extremely tedious) is:
a. Run the weather file as a Leap Year through Feb. 28th.
b. Create a new weather file where the dates are moved up by one, i.e., Jan 2 is
Jan 1, and so Feb. 29 is Feb. 28.
c. Run this new weather file picking a year where the Day of Week is the same as
the Leap year, starting with Feb. 28 (actually the 29th)

i.e., what you would be doing is

days in File1 Ian 1 ... Feb27 Feb28 Feb29 Mar1 Mar2 Mar3
Run 1 yes ... yes yes skipped no no no

days in FIle2 Jan 2 .. Feb26 Feb27 Feb28 Mar1 Mar2 Mar3
Run2 no .... no .... no yes yes yes yes

Joe

Joe Huang
White Box Technologies, Inc.
346 Rheem Blvd., Suite 205A
Moraga CA 94556
yjhuang at whiteboxtechnologies.com
http://weather.whiteboxtechnologies.com for simulation-ready weather data
(o) (925)388-0265
(c) (510)928-2683
"building energy simulations at your fingertips"

Bldg simulation's picture
Offline
Joined: 2016-04-13
Reputation: 400