eQuest unmet load and report help

3 posts / 0 new
Last post

hello,

I am working on a LEED submission, and I am seeing a very large % of hours
any system zone outside throttling range but zero percent of the plant load
is unsatisfied. Can someone explain what exactly the difference in these
numbers is? Also, does anybody have any idea what might cause such a large
discrepancy. My first thoughts were undersized equipment, but I'm hesitant
to lay blame on the HVAC contractor until I have fully verified my model.

Also, for LEED, they want the ES-D reports. It seems that for some of my
models .sim outputs, the ES-D report is not included, but is included for
others. Any thoughts?

Thank you for your help.

Marcus Eliason

Marcus Eliason's picture
Offline
Joined: 2011-09-30
Reputation: 0

Can you post your .inp and .pd2 files?

Steven Savich

Steven Savich's picture
Offline
Joined: 2011-09-30
Reputation: 200

I have attached the .inp and .pd2 files for this project for analysis.

Marcus Eliason's picture
Offline
Joined: 2011-09-30
Reputation: 0