T24 Standard building inputs?

2 posts / 0 new
Last post

An HTML attachment was scrubbed...
URL:

cic at jci.com's picture
Offline
Joined: 2011-09-30
Reputation: 0

Try this -

When compliance analysis initializes, you will get the following dialog.
If you check "Store Intermediate Simulation Models" all .inp files
should be saved. Note that the Title24 compliance process does not
generate individual .pd2 files for each input file. The naming
convention is:

"

T24 Proposed HVAC Sizing.inp" - created first, this
file is used to perform the sizing calculations for the proposed
building.

"

T24 Proposed Building.inp" - created second, this
file is used to generate the energy use of the proposed building

"

T24 Standard HVAC Sizing.inp" - created third, this
file is used to perform sizing calculations for the budget building

"

T24 Standard Building.inp" - created last, this file
is used to generate the energy use of the budget building

Kevin Madison PE

Kevin Madison2's picture
Offline
Joined: 2012-01-24
Reputation: 0