For what it?s worth, this feels closer to a [bldg-sim] question rather than one specific to doe2/eQUEST. You might more likely find a response under that forum ;-).
~Nick
[cid:image001.png at 01D3B56E.39744EB0]
Nick Caton, P.E., BEMP
Senior Energy Engineer
Regional Energy Engineering Manager
Energy and Sustainability Services
Schneider Electric
D 913.564.6361
M 785.410.3317
F 913.564.6380
E nicholas.caton at schneider-electric.com
15200 Santa Fe Trail Drive
Suite 204
Lenexa, KS 66219
United States
[cid:image002.png at 01D3B56E.39744EB0]
An HTML attachment was scrubbed...
URL:
Darryl,
I suggest checking the BC Hydro NCP Modeling Guidelines as well. Lots of good information on this webpage:
https://www.bchydro.com/powersmart/business/programs/new-construction.html
Christopher R. Jones, P.Eng.
Technical Specialist
Sustainability & Energy
[cid:image001.png at 01D3B601.5EAC2980]
T +1 416-644-0252
2300 Yonge Street, Suite 2300
Toronto, ON M4P 1E4 Canada
wsp.com
Please consider the environment before printing...