Dear All,

I am using following methodology for Baseline to Proposed comparison in equest:

1. First using eQuset creating Baseline model with the help of Appendix - G.

2. And then creating Proposed model by saving the baseline model and changing it with Proposed model data.

2. Then taking all the baseline model and Proposed model data in separate spreadsheet and comparing it.

Is it correct? Or I need to do something else?

Can I create Baseline and Proposed model in the same eQuest file and have comparison?

If somebody have answer please let us know. . . .

?
Thanks,

Nimesh Prajapati

Nimesh Prajapati Nimesh's picture
Joined: 2012-11-12
Reputation: 0

Nimesh it looks like you are on the front end of your performance rating
method journey.
A good place to begin would be the IBPSA Building Energy Modeling
Workshops. (downloadable .pptx)

http://www.bembook.ibpsa.us/index.php?title=Downloads

*Arpan Bakshi** *LEED AP BD+C, ESTIDAMA PQP

NYCCTgreen's picture
Offline
Joined: 2011-09-30
Reputation: 0