I saw an archive that said the following warning report would be removed
from future releases:
**WARNING*******************************************************************
***
Zone: 2354 (G.1) could not successfully
allocate all equipment energy to the 5-minute bins
because of an equipment overload. The peak load
used in ECONOMICS will not include the fraction due
to the overload, but the PLANT reports will.
Mon/Day/Hour: 1 28 6 Energy: 0.1 Unallocated: 0.000
Since it wasn't, does that mean I should be concerned about it?
Anthony Hardman
Hi all,
Is there some way to produce DOE-2 (input/output) Reports in the eQuest
Program?
Thanks,
Antonio
I trust someone responded to this already, however, in case noone did...
The .sim file contains the DOE-2 reports generated by eQUEST. You can
find them in the projects directory. You can also view them from within
the eQUEST interface by selecting View Simulation Output in the Tools menu.
Note that the .inp file is generated by eQUEST "dynamically".
Both the .inp and the .sim are text files. eQUEST comes with
D2SimViewer, a text viewer which will jump to the various DOE-2 reports
-- but any text editor will open the .sim.