I'm modeling a 30,000 sf addition to an existing building that's 3
floors above an existing 2 floor building. It has its own chiller and
natural gas boiler. In Table G3.1.1A should I select System3 assuming 3
floors, or should I select system 5 assuming 5 floors?

Vikram Sami, LEED AP

Vikram Sami's picture
Offline
Joined: 2011-09-30
Reputation: 0

Is just the addition going for LEED certification? Also, make sure no hvac
systems are connected with the existing building. Then probably system3.

Kevin Kyte, EIT, LEED AP

Kevin Kyte's picture
Offline
Joined: 2011-09-30
Reputation: 0

Well - actually the existing building is also going for certification
and is in the final processes. This is really its own separate building
- except for the fact that it sits directly above the other building.

Vikram Sami, LEED AP

Vikram Sami's picture
Offline
Joined: 2011-09-30
Reputation: 0